The historical Ernestina is heading toward completion of her major re-fit here at Boothbay Harbor Shipyard. With two months left before the launching of the Ernestina in April, the crew is working very hard to meet the deadline.
The planking covering the bow and midship is complete with the exception of one plank on the starboard side. With the completion of the planking, the chalking has begun on the hull. After the chalking is the sealing.
The building of the deck frame is nearly finished and the laying of the deck will begin shortly.
A template of the covering boards above the planking has been developed and the completion of the covering boards will be the next step toward wrapping up the Ernestina re-fit. Watch the VIDEO below showing the latest progress on the Ernestina